At the end of this week, our team will be moving into the testing phase where we will be troubleshooting any potential onsite problems that may have been unforeseen. We are also presenting our current status of the project this Wednesday. We will be highlighting (but not limited to) the following:
Due to the design of the braking system, the brackets we made became incompatible
We defaulted to the old brackets
We filled in the gaps of the older conductive rail
We have fully installed the conductive rails along the entire track
Proceeding to install collector shoes onto Bogie
An adapter will be made to secure the contacts between the collector and the track even further
Testing begins next week